    Route 1 & 9 – Pulaski

    Client: New Jersey Department of Transportation (NJDOT)

    Ferreira Construction replaced the bridge deck which included concrete repair areas of the entire deck from joint to joint, and utilized multiple Zimmerman Inc. Mobile Mixers, averaging approximately 4000 square feet of removal and replacement per weekend shift. An impressive element to the project, the key to Ferreira’s success, was the implementation of a mobile mixer concrete plant on site. With only a single lane available, the coordination of the cycle time for the concrete was critical as the joints could not get cold. Reminiscent of a construction “pit-crew”, the Ferreira team’s coordination efforts contributed to the project being completed on schedule.